- Beginning of construction August 1, 2020
- End of construction June 30, 2021
- Nature of building 3,300 sqm industrial hall with offices
- Customer Own development
- Category General contractor, Permitting designs




Building equipment, Construction work, Electrical installations, General contractor, Roads and public utilities, external paved areas of 10.000 m², Technological execution
Execution plan, General contractor, Permitting designs, Technological execution
Building equipment, Building permit documentation, Construction work, Electrical installations, Execution plan, General contractor, Occupancy permit, Official building permit, Road and utilities, Technological execution
Building equipment, Execution plan, Permitting designs, Road and utilities, Technological execution